Contract B: STATUS
MD 97 to US 29
Current Activities

Norbeck Road
- Erosion & Sediment Controls
- Utility Relocations (WSSC water and sanitary sewer, PEPCO, Verizon, Comcast, Washington Gas)
- Grading Work
- Excavation of embankment west of Norbeck Road
- Traffic switch and temporary signalization (anticipated December 2009)
- Reforestation- 8 acres (more than 1700 trees)

Longmead Crossing Drive
- Pile driving and support of excavation for bridge construction
- Utility Relocations and tie ins (WSSC)
- Grading Work
Layhill Road/MD 182
- Erosion & Sediment Controls
- Begin mainline pipe/culvert work
- Permanent bridge substructure construction, including pile driving to build bridge foundation
Bonifant Road/Northwest Branch
- Complete erosion and sediment controls
- Installation of haul roads for construction access
- Utility relocations & tie-ins (WSSC water)
- Pile driving to build bridge foundations
- Bridge substructure construction, including bridge columns and caps
Notley Road
- Stream diversion and installation of erosion and sediment controls
- Clearing of trees and brush
- Utility relocations (WSSC water, PEPCO, Verizon, Comcast)
New Hampshire Ave/MD 650
- Installation of erosion & sediment controls
- Utility Relocations - PEPCO, Comcast, Verizon, Montgomery County (signals, 911)
- Bridge construction, including pile driving to build bridge foundations
- Cape May Road - Permanently CLOSED to MD650 access, cul de sac construction
- Reforestation – 3 acres south of ICC alignment (126 trees)
East of New Hampshire Ave (Special Protection Area - SPA)
- Start of major construction activities anticipated in December
- Clearing of trees and brush
- Installation of erosion & sediment controls
- Soil Investigation/Soil Borings